New cruise ship pier completion date moved to November 2019

Basseterre, St. Kitts, October 23, 2019 (ZIZ News): The St. Christopher Air & Sea Ports Authority has announced a new date for the completion of the second cruise pier.

According to a statement from SCASPA the pier is expected to be completed on November 8.

Construction at Port Zante, was undertaken on a Government to Government arrangement between The Canadian Government and the Government of St Kitts and Nevis .

It began in March 2018, with completion initially scheduled for September 23, 2019.

According to a release from SCASPA on Wednesday work was interrupted in September following the passage of Tropical Storm Dorian .

The release also stated that damage was also done โ€œfurther south of the Federation resulting in significant damage to three on-site operating badges. The damage to these badges consequently delayed completion time for the second cruise ship pier.โ€

SCASPA informed that swift measures were immediately taken by the contractor to secure a replacement barge to complete the work and also confirmed that a barge has since been secured and is currently en-route to St. Kitts from the U.S.

The second cruise pier project will officially be completed on November to accommodate the 2019/2020 Cruise Season.